LiLA construction October - December 2025

Yes, it is named the UT Field Lab now, and yes, in October the official opening was held. Still, not all experiments are quite finished just yet. Most need some additional sensors aboveground, just like the green infrastructure project.

Our current timeline is to have the staircase installed. The foundation of steel was placed in December, which you can see in the photos below. Once this is finished, we can complete external sensor placement. At the end of January, the green roofs are to be constructed, so we do expect one more construction post before we can officially start data collection.





 